List of Major Works completed in the last 5 years(Scroll sideways to view full table) |
||||||
S.No. | Name of the Project | Name of the Client | Type of Project | Start Date | Finish Date | |
1 | Electrical works | TGiraffe Outlet in Rajiv Gandhi International Airport, Hyderabad under FL Traders Pvt. Ltd., Chennai |
Restaurant | May-2024 | Jul-2024 | |
2 | Electrical & ELV Works | TCH Retirement Home Private Limited" - Illam Senior Citizens Residence at Kadambadi, ECR, Chennai |
Residential Apartments | Aug-2022 | Jan-2024 | |
3 | Electrical HT & LT works | M/s. Lotus Ventures, Bangalore under Divinus Prime Projects India Pvt Ltd. |
Industry - IT/ITES/Retail/Hospitality | May-2022 | June 2024 | |
4 | Electrical works | Fresh and Healthy Outlet in KIAL, T2, Bengaluru under FL Traders Pvt. Ltd., Chennai |
Restaurant | Nov-2023 | Jan-2024 | |
5 | Electrical Works (First Floor & Infrastructure) | Omnex India Pvt Ltd, Thoraipakkam, Chennai |
Office | Sep-2023 | Dec-2023 | |
6 | Electrical Works | Multipurpose Hall com Renovation of office - Jacsons Meditech, KilPadappai, Chennai |
Auditorium / Office | Apr-2023 | Aug-2023 | |
7 | Electrical works - Additional Chiller / Additional Laundry Equipment / Allied CEIG works | EIH Associated Hotels - Trident, GST Road, Meenambakkam, Chennai |
Hotel | Mar-2023 | Oct-2023 | |
8 | Electrical Works | Farzi Café in KIAL T2, Bengaluru under FL Traders Pvt. Ltd., Chennai |
Restaurant | Mar-2023 | May-2023 | |
9 | Electrical Installation works | Jamuna Blood Centre, Korattur under Chandrayya Memorial Trust, Chetpet, Chennai |
Blood Centre | Dec-2022 | Mar-2023 | |
10 | Electrical & IT Works | Central Kitchen Outlet in KIAL, T2, Bengaluru under FL Traders Pvt. Ltd., Chennai |
Restaurant | Dec-2022 | Mar-2023 | |
11 | Electrical Works | La Madeleine Kiosk, KIAL, T2, Bengaluru under FL Traders Pvt. Ltd., Chennai |
Restaurant | Dec-2022 | Mar-2023 | |
12 | Electrical Works | Wolfgang Puck Outlet in KIAL, T2, Bengaluru under FL Traders Pvt. Ltd., Chennai |
Restaurant | Sep-2022 | Mar-2023 | |
13 | Electrical Works | Pizza Hut Outlet in KIAL, T2, Bengaluru under FL Traders Pvt. Ltd., Chennai |
Restaurant | Aug-2022 | Oct-2023 | |
14 | Electrical / IT & Security Works | Johnny Rocket's Outlet in KIAL, T2, Bengaluru under FL Traders Pvt. Ltd., Chennai |
Restaurant | Aug-2022 | Dec-2022 | |
15 | Electrical Works | Mercury Hospital Pvt. Ltd., Pantheon Road, Egmore |
Hospital | Jul-2022 | Jan-2023 | |
16 | Augmentation of Substation capacity by providing additional 630 KVA transformers and allied Substation equipments at AG(A&E) office, Teynampet, Chennai | CPWD, Thirumangalam |
Office | Apr-2022 | Dec-2022 | |
17 | Electrical Installations | Christian Mission Chariatable Trust, Padappai, Chennai |
Non Profitable Organization | Apr-2022 | Dec-2022 | |
18 | Charges for Supply, Installtion, Testing & Commissioning of Electrical & Diesel Generaror Package Works | M/s T1 & T2 Olympia Opaline Residential Apartments, Navalur, Chennai |
Apartments | Apr-2020 | Dec-2022 | |
19 | Electrical works pertaining to Transition of the existing 11 KV 400 KVA compact Substation to provide Electrical connections to a new Building including Supply & Installation of 630A Sandwich type Rising Main, LT Panels, LT Cables and Terminations, Distribution Boards, Cable Trays ,Switches & Sockets, Earthing, Lightning Protection system, Cabling of Data / Telephone / CCTV and allied works including CEIG approval. | Dr. Govindans Hospital, Trivandrum - Phase I of the Project |
Hospital | Aug-2020 | Mar-2022 | |
20 | Renovation in Electrical Installations | Christian Mission Chariatable Trust, Chetpet, Chennai |
Non Profit Organization | Oct-2020 | Dec-2021 | |
21 | Electrical Installations - Supply & Installation of Octogonal street light poles, high mast poles, LT cabling and its terminations, 415V power distribution boards, MCB distribution boards, Light fittings, Point Wiring, Earthing etc. | "Atomic Energy Central School at Zirconium Complex, Pazhayakayal, Tuticorin, Tamilnadu
" |
Educational Institution | Apr-2020 | Dec-2021 | |
22 | Supply and Installation of Ring Main Gear, 11 KV HT Panel, 1600 KVA Cast Resin Dry Type Transformer with OLTC & RTCC, 2500 A Bus Duct, 800 Amps, 630 Amps & 400 Amps Rising Main, Main LT Panel with 500 KVAR APFC Panel, Medical Equipment Panels, UPS Panels, Chiller Panel & Sub Panels, DBs’, Cables, Wires, Switches & Sockets, Earthing, External Lighting, 6M Street light Poles, Lightning Protection system & Installation of 2 x 625 KVA DG sets with exhaust piping, 275 KVA UPS, 500 KVA UPS, 30 KVA UPS and obtaining CEIG & TNEB approvals. ELV works including Nurse call system, TV system & Cable trays for ELV network cables | M/s Prashanth Fertility Research Centre Pvt. Ltd., Kolathur, Chennai |
Hospital | Oct-2019 | Feb-2022 | |
23 | Electrification including Lower side communication networks such as telephone, CCTV, camera etc. | Bungalow of Mr. Udayarkar, Injambakkam, Chennai |
Residence | Sep-2019 | Dec-2021 | |
24 | Charges for Supply, Installtion, Testing & Commissioning of Electrical & Diesel Generaror Package Works | M/s Olympia Amazon, Thirumazhisai |
Warehouse | Dec-2020 | Sep-2021 | |
25 | Electrical and Diesel Generator System Package Works SH: Providing HT & LT Cables and Terminations, Distribution Boards, Cable Trays, ,Switches & Sockets, Earthing, Lightning Protection system and allied works including Installation of 2000 KVA Transformer, HT Panels,2x1010 KVA DG set along with DGs’ exhaust piping, 3200 A & 2000 A Bus Ducts, 1600 A Rising Mains. | Olympia Inspire IT Park, Guindy, Chennai |
IT Park | Mar-2019 | Apr-2021 | |
26 | Electrical works – Supply, Installation, Testing & Commissioning of Electrical Works (Panels and Low Side Works) including LT Panels, MCB Distribution Boards, Isolators, LT Cables and Terminations, Cable Trays, Lightning Protection , Earthing, and allied works. | M/s Saravana (Tex) Gold Showroom, Purasaiwalkam, Chennai |
Showroom | Oct-2019 | Mar-2020 | |
27 | Electrical works at Third Floor – including LT Panels, MCB Distribution Boards, Internal & External Wiring for lights / fans & other Equipment, Isolators, LT Cables and Terminations, Cable Trays, Switches & Sockets, Lightning & Protection, Earthing, and allied works | Madras House Hotel AT VR Chennai, Chennai under Sugam Vanijya Holdings Pvt Ltd | Hotel | Jan-2019 | Aug-2019 | |
28 | Electrical works at Terrace - including outdoor LT Panel, Rising Main Tap off boxes, MCB Distribution Boards, LT Cables and Terminations, Cable Trays, Switches & Sockets, Earthing, and allied works. Erection of Outdoor light fixtures including Planter lights, Bollards, Swimming Pool lighting, Outdoor Event deck lighting, Tennis Court, Outdoor Bar area etc. | Feb-2019 | Aug-2019 | |||
29 | Electrical Works | Mr. Manoher Rao Residence at Gafoor Nagar, Madhapur, Hyderabad under Architect M/s Raj Expedith Associates | Residence | Oct-2017 | Sep-2019 | |
30 | Electrical Works - Providing IEI & fans i/c Service connection, solar water heaters, Lifts, Lightning conductors and Down comer system including LT Panels, MCB Distribution Boards, Bus Bar Trunking, Isolators, LT Cables and Terminations, Cable Trays, Cable Management Systems, Fire Alarm ,Switches & Sockets, Earthing, and allied works. |
IIT Palakkad (Under CPWD, Calicut) | Hostel | Apr-2017 | May-2019 | |
31 | Electrical works - Wiring / Cables / Distribution Boards / Cable Tray / Earthing / Light Fittings / Lightning Arrestor and allied works | The Park Residence, kotturpuram, Chennai | Residence | Apr-2015 | Mar-2019 | |
32 | Electrical works – Execution of Electrical works for External Services for Tower, Heritage, Deluxe block & Common areas and Execution of Low side Electrical Works for Renovation of Heritage Block (80 & 90 series), Tower Block, Corridors at Vivanta by Taj Connemara – Chennai, including 2 Nos. of 750 KVA Transformers, HT Panel, LT Panels, Rising Main, Bus Ducts, MCB Distribution Boards, Isolators, LT Cables and Terminations, Cable Trays, Switches & Sockets, Lightning & Protection, Earthing, and allied works | Taj Vivanta (Connemara Hotel), Chennai | Hotel | Nov-2016 | Feb-2019 | |
Oct-2017 | Feb-2019 | |||||
33 | Electrical works – 1600 KVA 11KV/ 433V Transformer, DG Synchronizing Panel, Bus Bar Trunking, Bus Ducts, MCB Distribution Boards, Isolators, LT Cables and Terminations, Cable Trays, Switches & Sockets, Earthing, and allied works. | M/s Parker Hannifin India Pvt. Ltd.,Chengalpet | Industry | Oct-2017 | Jul-2018 | |
34 | Electrical works - Wiring / Cables / Distribution Boards / Cable Tray / Earthing / Light Fittings / Lightning Arrestor and allied works | EI & Fans in New Government Medical College at General Hospital Compound, Thiruvananthapuram (Block I) | Medical College | Jul-2015 | Jan-2017 | |
35 | Electrical works - Wiring / Cables / Distribution Boards / Cable Tray / Earthing / Light Fittings / Lightning Arrestor and allied works | SairamDaya ( Mr. Raghunath Residence | Residence | Jun-2015 | Apr-2017 | |
36 | Electrical works - HT & LT Panels / DBs / Cables / Switches & Sockets / Data & Voice / External Lighting / Lightning Protection System / UPS System / Fire Alarm System / CCTV System / PA System/ EPABX System / DG Set and Allied works | M/s. Prashanth Hospitals, Velacherry ( Phase 2) | Hospital | Sep-2014 | Apr-2017 | |
37 | Electrical works - Panels / DBs / wiring / Cales / Terminations / Data / Voice / Lightning Protection system | Reji Jacob, Madipakkam | Office cum- Residence | Aug-2015 | Mar-2017 | |
38 | Electrical works - Panels / DBs / Cables / Switches & Sockets / Data & Voice / UPS System / DG Set and other allied works | Mr. Ajit Chhordia's Residence, Chennai | Residence | Aug-2013 | Aug-2015 | |
39 | Providing Internal Electrical Installation for Solar inverter | M/s. Swelect Energy Systems) M/s. IIITDM, Melakottayur | Institution | Aug-2015 | Oct-2015 | |
40 | Electrical works - Panels / DBs / Cables / Switches & Sockets / Data & Voice / UPS System and other allied works | Mr. Chetan Acharya's Residence, Chennai | Residence | Aug-2012 | Apr-2015 | |
41 | Electrical works - Panels, Cablwes, DBs, Cables, Terminations, Earthing. Light fittings, wiring, and other allied works | M/s. Caladium properties Pvt. Ltd., | Residence | Dec-2012 | Apr-2015 | |
42 | Electrical works / Panels and Panel Modification works Panels / distribution Boards / Cables / Cable Trays, Raceways Lightning protection System Rising Mains | Apollo Womens Hospitals, Shafi Mohammed Road, Chennai | Hospitals | Jun-2014 | Apr-2015 | |
43 | Electrical Works - Transformer, VCB Panels, LT Panels, HT & LT Cables and Cable Termination, Rising Main, Distribution Boards, Isolator, Earthing, Cable Tray, Wiring, Safety Equipments, Telephone / Data, Inverter, Lightning Protection System, Light Fixtures & DG System with Sync Panel and Accessories and allied works | M/s. Olympia Tech Park - Platina | IT Park | Jun-2013 | Nov-2014 | |
44 | Electrical works - Panels / DBs / Cables / Switches & Sockets / Data & Voice / External Lighting / Lightning Protection System / Raceways / UPS System and allied works | M/s. IBIS Hotels, Chennai | Hotel | Jan-2013 | Oct-2014 | |
45 | Internal Electrical Installations and fans, Data Cabling, Day light & Occupancy sensors etc at Lecture Hall |
IIITD&M, Melakkottaiyur, Kancheepuram District.- | Educational Institution | Aug-2013 | Oct-2014 | |
46 | Electrical works - SITC of 2 x 500KVA of Substation Equipment for Substation No. III | IIITD&M, Melakkottaiyur, Kancheepuram District.- | Educational Institution | Jan-2014 | Oct-2014 | |
47 | Electrical works - 25 KVAR Capacitor and 400A Contactors | Chennai Trade Centre, Nandambakkam, Chennai | Exhibition Hall | Feb-2014 | Apr-2014 | |
48 | Electrical Works - Motion sensors at V to IX Floors | M/s. RBS Business Services Pvt. Ltd, Olympia Tech Park, Guindy | Bank | Sep-2013 | Jan-2014 | |
49 | Electrical works – Panels, DBs, Street Light Poles, Earthing, cables and terminations, Inverter, Light fittings etc. |
Beach House, ECR, Chennai |
Residence |
Dec-2012 | Oct-2013 | |
50 | Electrical works - Panels / DBs / Cables / Switches & Sockets / Data & Voice / External Lighting / Lightning Protection System / UPS System | M/s. Prashanth Hospitals, Velacherry ( Phase 1) | Hospital | Jul-2012 | Sep-2013 | |
51 | Electrical Works LT Panels, MCB DBs, Cable & Terminations , Earthing , Safety Equipments, Light Fittings, Wiring, Inverter and allied works | Mr. Selvakumar Residence, Palavakkam | Residence | Sep-2012 | May-2013 | |
52 | 11KV HV/MV Electrical Installation: a. 11KV VCB Panel, LT Panel, 800KVA Transformer, 11KV USS, 500KVA DG Set, Distribution Boards, Cables, Termination, Earthing, Lightning Protection System, Light Fittings, LV Systems, |
Union Bank of India, Broadway, Chennai | Bank |
Jun-2011 | May-2013 | |
53 | Electrical External Infra Strcture work : Panels / RMG / 200 KVA Transformer / Distribution Boards / Earthing / Cables / Terminations / Light Fixtures / Lightning Protection System / Allied works | The Orchids, M/s. Rakindo Township Pvt. Ltd., Phase 1, Madhukkarai, Coimbatore | Residential Apartments | Apr-2012 | Apr-2013 | |
54 | Electrical works : Panels / Cables / Termination / Cable Trays | M/s. CIPET, Guindy | Institution | Dec-2011 | Jan-2013 | |
55 | Electrical works - EB & DG Changeover Panel / Primary Distribution Board / APFC Panel/ Cables/ wirings/ Earthing / Cable Management System | M/s. Music School, Santhome | Institution | May-2012 | Jan-2013 | |
56 | Electrical Works LT Panels, DBs, Cable & Terminations, Earthing , Safety Equipments, Light Fittings,Wiring,Lightning Protection & allied work | Mr. Reji Jacob Residence, Madipakkam | Residence | Oct-2012 | Dec-2012 | |
57 | Interior Fitout works: Panels, Distribution Boards, Light Fittings, Cables, Earthing, Cable Trays etc. |
M/s. Qualcomm,TVH Agnitio IT Park | IT Park | Apr-2012 | Aug-2012 | |
58 | Electrical works – Panels, DBs, Street Light Poles, Earthing, Light Fittings, cables, terminations etc. | ECR Farm House, Chennai |
Residence |
Jun-2011 | Jul-2012 | |
59 | Electrical works - 11 KV RMG (Outdoor), 11 KV Single VCB Panel, 11KV HT Three Panel Board (Indoor), Maintenance Panel, DBs, Cables, Terminations, Earthing, Light fittings, Lightning Protection System | M/s. Parker Hannifin India Pvt. Ltd., Mahindra World City | Panel Automation Factory | Aug-2011 | Jul-2012 | |
Additional works: | ||||||
a | Electrical connection in Assembly cell area | Dec-2012 | Jan-2013 | |||
b | electrical works associated with the 125KVA DG Set and Downstream electrical Distribution | Dec-2012 | Jan-2013 | |||
c | electrical works at Media room Area | Apr-2013 | Apr-2013 | |||
d | Electrical works for Test Lab Rig Machine area, | Jun-2013 | Jun-2013 | |||
e | Maintenance Panel and its allied works | Jul-2013 | Jul-2013 | |||
f | 125A Junction Box, Testing of Earth electrodes and earth pits, cables and allied works | Dec-2013 | Jan-2014 | |||
Total Additional works | ||||||
60 | 180 KVA DG Sets & allied works | M/s. Marjan Motors, Arumbakkam, Chennai | Show Room | Nov-2011 | Apr-2012 | |
61 | Electrical Upgradation works | M/s. RBS Business Services Pvt Ltd., KRM Towers, Chetpet, Chennai | Bank | Nov-2011 | Mar-2012 | |
62 | Electrical works - MV Panel / Cables / Earthing and allied works | M/s. Vaikund Estates, Chennai | Printing Press | Jun-2011 | Dec-2011 | |
63 | Electrical Upgradation works | M/s. RBS Business Services Pvt Ltd., Olympia Tech Park, Guindy, Chennai | Bank | Nov-2011 | Mar-2012 | |
64 | Erection of Capacitor Panel and allied works | M/s. Galfan Engineers Pvt. Ltd., Chennai | Factory | Nov-2011 | Jan-2012 | |
65 | Electrical works (Additional works) - Distribution Boards, Cables, Static Transfer Switch etc., | The World Bank, Taramani, Chennai | Bank | Jun-2011 | Nov-2011 | |
66 | Electrification for Industry - 1x630KVA Transformer, 1* 365 DG Set Allied HT Panels,LT Panels & Bus Ducts, Cabling & Termination, Lighting Protection |
M/s. MOC Dies & Moulds, Chennai | Industry | Sep-2010 | Aug-2011 | |
67 | 5 Star Hotel with 171 Guest Rooms, Lobby, Restaurants, Kitchen etc. 1 x 630KVA Transformer, Rising Mains, Cabling, Cable Trays, Earthing, DG Set , TV System, Net working system, Lightning Protection System, Wiring and allied works |
M/s. Aloft Hotels, Coimbatore |
Hotel | Jun-2010 | Aug-2011 | |
68 | Interior Fitout works: Panels, Distribution Boards, Light Fittings, Cables, Earthing, Networkings Fire Alarm Systems, etc. |
M/s. Areva Bio-Energy India Pvt. Ltd., Maraimalai Nagar, Kancheepuram |
Industry | Nov-2010 | Mar-2011 | |
69 | DG Changeover Panel, Cables and Terminations and Earthing | M/s. RBS Business Services Pvt. Ltd., | IT - Infrastructure | Oct-2010 | Nov-2010 | |
70 | Panels, UPS, Distribution Boards, Cables and wiring, Earthing, Light Fixtures and Cable Trays etc | The World Bank, Chennai | IT - Interior fitouts | Nov-2009 | Aug-2010 | |
71 | Electrical Installation including HV/LV electrical equipments like Panels, DBs, Transformers, DG Sets, Fire Alarm System, Public Address System | M/s. Prashanth Multi Speciality Hospitals, Harrington Road, Chetpet, Chennai | Hospital | Nov-2008 | May-2010 | |
72 | Hyundai 3S Facility Centre at Sholinganallur, Chennai with Transformer, HT and LT Panels, DG Sets, DBs Networking like Public Address System, Light Fittings, Cables, Cable Trays, Wiring etc | M/s. Marjan Motors, Sholinganallur | 3 S - Show room for Hyundai- Infrastructure & Interior fitouts | Jul-2009 | May-2010 | |
73 | 3 Star Hotel with 134 Guest Rooms, Lobby,Restaurants,Kitchen,1x1000KVA Transformer,2 x 365 KVA DG Sets,Rising Main,Busducts,Cabling, Cable Trays, Earthing, Wiring works | M/s. Aloft Hotels, Sholinganallur | 3 Star Hotels - Infrastructure & Interior fitouts | Jun-2009 | May-2010 | |
74 | Panels, UPS, Distribution Boards, Cables and wiring, Earthing, Light Fixtures and Cable Tray Fire Alarm Systems and other allied works | M/s. MacawFx Films Pvt. Ltd. Hyderabad | Training Centre - Interior fitouts | Feb-2010 | Apr-2010 | |
75 | Renovation of Wiring works | M/s. Nippon, Santhome | Photo Lab cum Show Room | Dec-2009 | Jan-2010 | |
76 | Panels, UPS, Distribution Boards, Cables and wiring, Earthing, Light Fixtures and Cable Trays | Bharti Airtel Ltd., First Floor, Siruseri | Telecom - Data Centre - Interior fitouts | Oct-2009 | Nov-2009 | |
77 | Panels,UPS, DBs,Cables & wiring, Earthing,Light Fixtures, Cable Trays | M/s. Bharti Airtel Ltd., Santhome, Chennai | Data Centre -Interior fitout | Oct-2009 | Nov-2009 | |
78 | Panels, Switch Boards, cables and lighting works | M/s. Nippon TTK Road, Chennai | Photo Lab cum Show Room - Interior fitouts | May-2009 | Aug-2009 | |
79 | Panels, Transformers, Distribution Boards, Light Fittings, Cables and earthing etc. | M/s. ABN AMRO N.V. at KRM Towers, Chetpet, Chennai | IT - Interior fitouts | Nov-2008 | Mar-2009 | |
80 | Data Centre Building at Siruseri, Infrastructure electrical works including 2 x 1250KVA + 4 X 1600KVA Transformer, 2 X 1100 KVA + 4 X 2000 KVA DG Sets, HT/LT Cables, sandwich type Rising Mains & Bus Ducts,Cable trays,Earthing etc | Bharti Airtel Limited 101, Santhome High Road, Chennai 600 028 | Telecom - Data Centre - Infrastructure | Aug-2007 | Dec-2008 | |
81 | HV/MV installation including transformers, generators, LT switch boards, cabling, earthing etc | Fairmont Hotel, Electronic City, Bangalore | 5 Star Hotels - Infrastructure & Interior fitouts | Apr-2008 | Dec-2008 | |
82 | 630 KVA Unitised Substation, 2 x 500 KVA DG Sets, 100 KVA UPS, LT Power and Lighting etc | Konica Laboratory Nungambakkam Chennai | Photo Lab cum Show Room | Jun-2007 | Nov-2008 | |
83 | HT/LT//LV installation for office cum factory premises inclusive of 2x500 KVA Transformer,1 x 500 KVA DG. All LV installation including access control, CCTV, Fire Alarm, PA System, Voice and Networking system | Diab Core Materials India P Ltd., Sriperumpudur. (90000 Sq.ft.) | Industrial - Infrastructure & Interior fitouts | Oct-2007 | Jul-2008 | |
84 | 3x 1600KVA Trfrs., 3 x1500KVA DG sets, LT Panels, HT/LT Cables, sandwich type Rising Mains and Bus Ducts, Cable trays, Earthing (Ph I) | TCG Developments India Pvt. Ltd. 108, Chennai 600 116 | IT - Infrastructure | Sep-2007 | Jun-2008 | |
85 | MV Switchgears, DBs, Fire Alarm system, Computer Data Cabling & HVAC Works etc | Trident Hilton, Health Club, Chennai | 5 Star Hotels - Infrastructure & Interior fitouts | Jan-2008 | Jun-2008 | |
86 | Raceways – Electrical. & Data including LT Panels, Auto Change over Panels,DBs,Wiring for Lighting, Raw Power & UPS,Cable Trays,Cable Ducts (Net working),Cabling,Earthing, Light Fittings, Switch & sockets for IT Office cum Server,Hub Rooms. UPS Systems: 4 X 60 KVA + 4 X 80 KVA | E-bay (M/s. Paypal India Pvt. Ltd.), Rama Rao Road, (Behind Nageswara Park) Mylapore, Chennai – 4 (1,50,000 q.ft.) | IT - Raceways | Aug-2007 | May-2008 | |
87 | Five Star Hotel – Thanjavur Restaurant including Lighting, Dimmers, Power, UPS, Telephone, Networking, Fire Alarm | Trident Hilton 1/24,Meenambakkam, Chennai | 5 Star Hotels - Infrastructure & Interior fitouts | Jul-2007 | Oct-2007 | |
88 | 630 KVA Unitised Substation, 2 x 500 KVA DG Sets, 100 KVA UPS, LT Power and Lighting and associated works with specialized systems for MRI, CT Scans | M/s. Lister Laboratories Chennai | Medical Laboratory | Jan-2007 | Sep-2007 | |
89 | Floor raceways & Internal works (7th Floor)including LT Panels,lighting,raw power,UPS wiring, raceways,cable trays,cabling, earthing etc. | ABN Amro Central Enterprises Pvt. Ltd., Olympia Tech Park, Ph II, Chennai | IT - Interior Fitouts - Electrical | Jun-2006 | Mar-2007 | |
90 | 3 x 2500KVA transformers, 4 X 1500KVA DG sets, HT/LT Cables, sandwich type Rising mains and bus ducts, Cable trays, Earthing and allied electrical works (Phase II) | Khivraj Tech Park Pvt. Ltd., Chennai (6,50,000 Sq.Ft.) | IT - Infrastructure | May-2006 | Mar-2007 | |
91 | 2x2000KVA Transformers, 5x1010 KVA DG sets, HT/LT Cables, Air insulated type Rising Mains and Bus Ducts, Cable trays, Earthing etc | GMR Varalakshmi Tech Park OMR Chennai (2,40,000 Sq. ft.) | IT - Infrastructure | Dec-2005 | Mar-2007 | |
92 | Floor raceways (5 Floors) | ABN Amro Central Enterprises Pvt. Ltd., Olympia Tech Park, Chennai (105,000Sq.Ft.) | IT - Floor Raceways | Jun-2006 | Mar-2007 | |
93 | (3 Floors) including LT Power and Lighting DB, Auto Change over Panels, Rising Mains . Wiring for Lighting, Raw Power & UPS, Cable Trays, Cable Ducts (Net working), Cabling, Earthing, Light Fittings, Switch & sockets, PA Systems and associated works Etc. UPS Systems: 2 X 120 KVA + 4 X 60 KVA | ABN Amro Central Enterprises Pvt. Ltd., Olympia Tech Park, Chennai (105,000 Sq.Ft.) | IT- Interior fitouts | Jun-2006 | Mar-2007 | |
94 | Additional Class Rooms including wiring for lighting, power and UPS, DBs for class rooms. Distribution arrangements for incorporating an additional DG set (380 KVA) & for a 100 TR chiller | American International School, Taramani, Chennai (30,000 Sq.Ft.) | International School - Interior fitouts | Aug-2006 | Dec-2006 | |
95 | LT Power and Lighting DB, Change over Panel, Wiring, Cabling, Earthing, Light Fittings, Switch & sockets, PA Systems etc | M/s. Citibank, Club House Road, Anna Salai, Chennai | Bank | Oct-2006 | Nov-2006 | |
96 | LT Power, Lighting and UPS DB, Main Panel, Wiring, Cabling, Earthing, Light Fittings, Switch & sockets and associated works Etc. | M/s. Videsh Sanchar Nigam Limited, Coimbatore | IT - Interior Fitouts | Sep-2006 | Oct-2006 | |
97 | IT Office space including 1 X 800 KVA Transformer, 2 X 500 KVA DG sets, Main LT Panel, Bus Ducts, LT Panels, wiring for lighting, raw power, UPS. Raceways,cable trays, cabling, earthing, switchboards,DBs | M/s. Honeywell Technology Solutions Lab Pvt. Ltd. Madurai (1,20,000Sq.ft.) | IT - Infrastructure and Interior fitouts | Jan-2006 | Oct-2006 | |
98 | Floor raceways (3 Floors) Internal electrical works ( 3 Floors) including LT Power and Lighting DB, Auto Change over Panels, Rising Mains . Wiring for Lighting, Raw Power & UPS, Cable Trays, Cable Ducts (Net working), Cabling, Earthing, Light Fittings, Switch & sockets, PA Systems etc. UPS Systems: 2 X 300 KVA + 1 x 200 KVA | Hewlett Packard Global Soft Ltd. Olympia Tech Park, Ekkaduthangal, Chennai 1.20.000 Sq.ft | IT - Interior fitouts | Apr-2006 | Sep-2006 | |
99 | 2 x 2000 KVA + 2500KVA transformers, 4 X 1500KVA DG sets, HT/LT Cables, sandwich type Rising mains and bus ducts, Cable trays, Earthing etc (Phase I) | Khivraj Tech Park Pvt. Ltd., Chennai (8,00,000 Sq.Ft.) | IT - infrastructure | Aug-2005 | Mar-2006 | |
100 | IT Office including commissioning of Switch Boards, DBs, lighting,UPS/Raw Power Circuits, raceways, Cabling, Earthing, Water sprinkler, Fire Alarm & P.A. Systems. | Amazon Software Development Centre (India) Pvt. Ltd., Old Mahabalipuram Road, Chennai. (10,000 Sq.Ft) | IT - Interior fitouts | Oct-2005 | Feb-2006 | |
101 | \HV/MV installation including transformers, generators, LT switch boards, cabling, earthing etc. | Fairmont Hotels, Bangalore(2,40,000 Sq.Ft.) | 5 Star Hotel - Infrastructure and Interior fitouts | Jun-2005 | Feb-2006 | |
102 | Supply and erection of floor raceways. | Verizon, C/o Khivraj Tech Park Pvt. Ltd. Chennai(1,00,000Sq.ft.) | IT - Interior fitouts | Dec-2005 | Jan-2006 | |
103 | Switch Boards, DBs, lighting, UPS/Raw Power Circuits, raceways, Cabling, Earthing. | Premedia Global India P Ltd.Temple Steps, 3rd Floor,Guindy-8000Sq.ft | IT - Interior fitouts | Dec-2005 | Jan-2006 | |
104 | Switch Boards, DBs, lighting, UPS/Raw Power Circuits, raceways, Cabling, Earthing. (8000 Sq.Ft.) | Leighton Contactors India Pvt.Ltd. Chennai. | IT - Interior fitouts | Dec-2005 | Jan-2006 | |
105 | Lighting, raw power,UPS wiring, raceways,cable trays,cabling, earthing | Hewitt C/o Khivraj Tech Park Pvt. Ltd. Guindy Indsl Estate, Chennai (25000 Sq.ft.) | IT - Interior fitouts | Nov-2005 | Dec-2005 | |
106 | Electrical works for Restaurant, Boiler Plant, Business Center and Banquet | Trident Hilton, Chennai | 5 Star Hotels - Interior fitouts | Apr-2005 | Sep-2005 | |
107 | Lighting, raw power, UPS wiring, raceways,cable trays, cabling, earthing etc. | ABN Amro Bank (Lords 1), Chennai (Area = 40,000 Sq.Ft.) | IT - Interior fitouts | Aug-2005 | Sep-2005 | |
108 | Electrical work for incubation space, Lighting, raw power, UPS wiring, raceways,cable trays,cabling, earthing | HP(Lords 2),Chennai (36000 Sq.Ft.) | IT - Interior fitouts | Aug-2005 | Sep-2005 | |
109 | Electrical work for incubation space, lighting, raw power, UPS wiring, raceways,cable trays,cabling,earthing | Panasonic India Pvt. Ltd, Chennai (8000 Sq.Ft.) | IT - Interior fitouts | Aug-2005 | Sep-2005 | |
110 | Internal electrical works for new PAN ASIAN Restaurant and BAR | Taj Connemara, Chennai | 5 Star Hotels - Interior fitouts | Jan-2005 | Aug-2005 | |
111 | HT/LT//LV installation for office cum factory premises inclusive of 800 KVA Transformer, 500 KVA and 180 KVA DG sets. All LV installation including access control, CCTV, fire alarm, public address and networking system | M/s. Grundfos Pumps India Pvt. Ltd.(Office = 75000 Sq.Ft. Factory = 80,000 Sq.Ft.) | Industrial - Infrastructure and Interior fitouts | Sep-2004 | May-2005 | |
112 | Electrical work for incubation space including all allied switchboards and DBs for lighting, Power and UPS DB, raw power, UPS wiring, raceways, cable trays, cabling, earthing etc. | M/s. Videsh Sanchar Nigam Ltd. 2 & 3 (Area = 25000 Sq.ft) | IT - Interior fitouts | Oct-2004 | Jan-2005 | |
CTB Block, New Warehouse Office. | Feb-2005 | Feb-2005 | ||||
113 | Turnkey electrification of 13 Floor, 3 Star hotel for Deccan Park Plaza Hotel comprising of 2 Nos. 630KVA Transformer, 2 Nos. 500 KVA DG Sets, complete HV/MV/LV installation for public and service area, banquet, restaurant,bar,100 Guest Rooms | M/s. Deccan Park Hotel (210000 Sq.Ft.) | 5 Star Hotels - Infrastructure & Interior fitouts | Aug-2004 | Jan-2005 | |
114 | Back office IT operations of the Bank at Raheja Towers Chennai - Lighting, UPS, Raw power wiring , raceways, switchboards, DBs, DG Sets, UPS installations, Earthing, cabling etc. | M/s. ABN AMRO Central Enterprises Services (P) Ltd. (400000 Sq.Ft.) | IT - Interiror Fitouts | 2005 | 2005 | |
2004 | 2004 | |||||
2003 | 2003 | |||||
2002 | 2002 | |||||
115 | HT/MV Installation of IT Office cum switch building including interior electrical works for lighting, UPS, Rawpower, raceways, switch Boards, DBs, DG sets, Transformers, HT panels, Earthing, Cabling etc. | Tata Tele Services Ltd. Trivandrum | Telecom - Switch Infrastructure & Interior Fitouts | 2005 | 2005 | |
Chennai | 2004 | 2004 | ||||
Madurai | 2003 | 2003 | ||||
Chennai | 2002 | 2002 | ||||
140000 Sq.ft.) | ||||||
116 | 2 Nos. 500 KVA (11 KV) Transformers, 2 Nos. 500 KVA DG sets, fully automatic LT panel with electrical interlocking AMF panels, cabling, wiring and LV systems for telephones, computer and CCTV system. | Taj Malabar Hotel Phase 2 | 5 Star Hotels - Infrastructure & Interior fitouts | 2004 | 2004 | |
Phase 1(Area =3,50,000 Sq.Ft.) | 2002 | 2002 | ||||
117 | IT Office in 8th Floor for 180 computer stations with related UPS electrical lighting and power wiring including public address system, fire fighting, data and voice networking works. | HCL Comnet Ltd (16,000 Sq.Ft.) | IT - Interior fitouts | 2004 | 2004 | |
118 | Turnkey HT and LT installation of American School at Taramani comprising of 1 No. 1250 KVA 11 KV/433V Transformer & 3 Nos. Generators of ratings 750, 500 and 250 KVA all electrically interlocked and other downstream / related works. | American International School, Chennai (2,50,000 Sq.ft.) | International School - Infrastructure & Interior fitouts | 2002 | 2003 | |
119 | Five Star Hotel with substation, DG sets, Boiler Plant, Chillers, Cooling Towers,Laundry,Kitchen,PA System, Restaurant,Business Centre,Banquet | Trident Hilton, Chennai | 5 Star Hotels - Infrastructure & Interior fitouts | 2005 | 2005 | |
2004 | 2004 | |||||
2003 | 2003 | |||||
2002 | 2002 | |||||
120 | Source changeover system & modification of LT panels | Alcoa CSI Nepal (P)Ltd | Industrial - Infrastructure | 2002 | 2002 | |
121 | Internal electrification for World Bank Group Office including commissioning of 2 Nos. 320 KVA DG Set with AMF Panel with Automatic Changeover. | World Bank Group Office( 40,000 Sq.Ft.) | IT - Interior fitouts | 2002 | 2002 | |
122 | 2nos. 630 KVA, 11KV OLTC transformers with remote tap changer cubicle (RTCC) ; 2nos. 750KVA DG Sets with AMF Panels for automatic Changeover.; 2nos. 1250A indoor busducts with flexibles Fully automated MV Panel with Electrical Interlocking for Automatic Changeover from EB to DG Complete LT Distribution, including all LT panels,cables & distribution boards Earthing works as per IS-3043, lightning arresters, indoor & outdoor lighting for Restaurants, Meeting Rooms,Lobby Swimming Pool, Guest Rooms, Kitchen, Laundry,Plant Room and Landscape areas | Trident Hilton, Cochin ( 4,00,000 Sq.Ft.) | 5 Star Hotels - Infrastructure & Interior fitouts | 1999 | 2001 | |
123 | (22KV/6.6KV/433V) for Modification of Seventh Berth of the Tuticorin Port Trust, for M/s.PSA-SICAL Terminals Ltd., Tuticorin (A Joint Venture between Port of Singapore Authority & South India Corpn (Agencies) Ltd.) | PSA - Sical Terminals Ltd. | Port - Container Terminal - Infrastructure and Interior fitouts | 1999 | 2000 |